Groundwater Progress Report - January 2015

GROUNDWATER PROGRESS REPORT – January 2015
Groundwater Progress Report for the Roche-Nutley site was submitted to the New Jersey Department of Environmental Protection in January 2015. The report reflects data from the third/fourth quarters of 2013 and the first/second quarters of 2014. Following are links to the report and its extensive support documents.  

NOTE: Some of the following documents are large and may take time to load, depending on your bandwith. If you zoom in, you may need to scroll to the right to see the pages.

REPORT:  Groundwater Progress Report (January 2015)

MAPSEstimated groundwater maps from quarterly sampling. Please note: the estimations may fluctuate over time due to seasonal variations and other conditions.
2013 - third quarter estimated map
2013 - fourth quarter estimated map
2014 - first quarter estimated map
2014 - second quarter estimated map


FIGURES

Figure 1 - Site Location Map
Figure 2 - NJDEP GIS Land Use Cover Map
Figure 3 - NJDEP GIS Landscape Project Map
Figure 4 - Regional Topographic Map
Figure 5 - Site Plan with IA and Surface Water Bodies
Figure 6 - NJDEP GIS and National Wetlands Maps
Figure 7 - Regional Surficial Geology Map
Figure 8 - Regional Bedrock Geology Map
Figure 9-1 - Monitoring Well Location Map
Figure 9-2 - Monitoring Well Location Map
Figure 10 - Orientation Bedrock Structures
Figure 11 - GWE Zone S1 12-12-13
Figure 12 - GWE Zone S2 12-12-13
Figure 13 - GWE Zone S3 12-12-13
Figure 14 - GWE Zone D1 12-12-13
Figure 15 - GWE Zone D2 12-12-13
Figure 16 - GWE Zone D3 12-12-13
Figure 17 - GWE Zone S1 Q1 2014
Figure 18 - GWE Zone S2 Q1 2014
Figure 19 - GWE Zone S3 Q1 2014
Figure 20 - GWE Zone D1 Q1 2014
Figure 21 - GWE Zone D2 Q1 2014
Figure 22 - GWE Zone D3 Q1 2014
Figure 23 - GWE Zone S1 Q2 2014
Figure 24 - GWE Zone S2 Q2 2014
Figure 25 - GWE Zone S3 Q2 2014
Figure 26 - GWE Zone D1 Q2 2014
Figure 27 - GWE Zone D2 Q2 2014
Figure 28 - GWE Zone D3 Q2 2014
Figure 29 - VFN A-A Q4 2013
Figure 30 - VFN B-B Q4 2013
Figure 31 - VFN C-C Q4 2013
Figure 32 - VFN D-D, E-E Q4 2013
Figure 33 - VFN F-F Q4 2013
Figure 34 - VFN A-A Q1 2014
Figure 35 - VFN B-B Q1 2014
Figure 36 - VFN C-C Q1 2014
Figure 37 - VFN D-D, E-E Q1 2014
Figure 38 - VFN F-F Q1-2014
Figure 39 - VFN A-A Q2 2014
Figure 40 - VFN B-B Q2 2014
Figure 41 - VFN C-C Q2 2014
Figure 42 - VFN D-D, E-E Q2 2014
Figure 43 - VFN F-F Q2 2014
Figure 44 - VFN G-G Q2 2014
Figure 45 - VFN H-H, I-I Q2 2014
Figure 46 - CVOC Plumes S1 Q4 2013
Figure 47 - CVOC Plumes S2 Q4 2013
Figure 48 - CVOC Plumes S3 Q4 2013
Figure 49 - CVOC Plumes D1 Q4 2013
Figure 50 - CVOC Plumes D2 Q4 2013
Figure 51 - CVOC Plumes D3 Q4 2013
Figure 52 - CVOC Plumes D4 Q4 2013
Figure 53 - CVOC Plumes S1 Q1 2014
Figure 54 - CVOC Plumes S2 Q1 2014
Figure 55 - CVOC Plumes S3 Q1 2014
Figure 56 - CVOC Plumes D1 Q1 2014
Figure 57 - CVOC Plumes D2 Q1 2014
Figure 58 - CVOC Plumes D3 Q1 2014
Figure 59 - CVOC Plumes D4 Q1 2014
Figure 60 - CVOC Plumes S1 Q2 2014
Figure 61 - CVOC Plumes S2 Q2 2014
Figure 62 - CVOC Plumes S3 Q2 2014
Figure 63 - CVOC Plumes D1 Q2 2014
Figure 64 - CVOC Plumes D2 Q2 2014
Figure 65 - CVOC Plumes D3 Q2 2014
Figure 66 - CVOC Plumes D4 Q2 2014
Figure 67 - CVOC A-A Q4 2013
Figure 68 - CVOC B-B Q4 2013
Figure 69 - CVOC C-C Q4 2013
Figure 70 - CVOC D-D, E-E Q4 2013
Figure 71 - CVOC F-F Q4 2013
Figure 72 - CVOC A-A Q1 2014
Figure 73 - CVOC B-B Q1 2014
Figure 74 - CVOC C-C Q1 2014
Figure 75 - CVOC D-D, E-E Q1 2014
Figure 76 - CVOC F-F Q1 2014
Figure 77 - CVOC A-A Q2 2014
Figure 78 - CVOC B-B Q2 2014
Figure 79 - CVOC C-C Q2 2014
Figure 80 - CVOC D-D, E-E Q2 2014
Figure 81 - CVOC F-F Q2 2014
Figure 82 - CVOC G-G Q2 2014
Figure 83 - CVOC H-H, I-I Q2 2014
Figure 84 - CVOC Quad View S1
Figure 85 - CVOC Quad View S2
Figure 86 - CVOC Quad View S3
Figure 87 - CVOC Quad View D1
Figure 88 - CVOC Quad View D2
Figure 89 - CVOC Quad View D3
Figure 90 - CVOC Quad View D4

 

TABLES

Table 1-1
Table 1-2
Table 1-3
Table 1-4
Table 1-5
Table 2-1
Table 2-2
Table 2-3
Table 2-4
Table 3
Table 4
Table 5-1 Q1
Table 5-1 Q2
Table 5-1 Q4
Table 5-2
Table 6-1
Table 6-2
Table 6-3
Table 6-4
Table 6-5


APPENDICES

Appendix A - Response to Comments
Response to NJDEP May 2014
Response to NJDEP September 2014

Appendix B - Monitoring Well Documentation
Form A Monitoring Wells
Form B Monitoring Wells
Permits Monitoring Wells
Records Monitoring Wells
Form A Remedial Wells
Form B Remedial Wells
Permits Remedial Wells
Records Remedial Wells
Well Logs Combined

Appendix C - ARM Geophysics Report

Appendix D - Temporary Well Map

Appendix E - NJDEP Well Contour Reporting Forms

Appendix F - PDB Sampling Forms and LF Measurements
PDB Information Table
Low Flow Add-Ons

Appendix G - PDI Reports
IA-2
IA-3&7
IA-9
IA-10 Building 104
IA-11 BR
IA-12
IA-15

Appendix H - Note

Appendix I - Hydraulic Conductivity Calculations
Table
TW Packer Sampling

Appendix J - Trend Analysis Concentrations
Composite Map
Concentrations vs GW

Appendix K - Interim Natural Attenuation Report
a. Summary of Hydraulic Conductivity Estimates
b. Roche Sitewise GW Results Sept13-Aug14
c. Field Parameters
d. Microseeps
d. Microbio Analysis
e. Microseep Lab Reports
e. Text Table
e. Zymax Lab Reports
Table 1
Table 2
Table 3
Table 4
Table 5
Interim NA Report
Figures - Interim NA Report

 

All documents and reports submitted to the New Jersey Department of Environmental Protection (NJDEP) for the environmental investigation and remediation of the former Roche Nutley site are available through NJDEP:  http://www.nj.gov/dep/opra/

About Nutley

 

Privacy Policy     Legal Statement     © 2012 F. Hoffmann-La Roche Ltd     27.04.2017

 

This website contains information on products which is targeted to a wide range of audiences and could contain product details or information otherwise not accessible or valid in your country. Please be aware that we do not take any responsibility for accessing such information which may not comply with any legal process, regulation, registration or usage in the country of your origin.